ILLINOIS REGISTER 3736
09
ILLINOIS COMMERCE COMMISSION
NOTICE OF PROPOSED RULES
3) The applicant provides a certificate of completion (see Appendix A) to the
EDC. Completion of local inspections may be designated on inspection
forms used by local inspecting authorities; and
4) The witness test is successfully completed if required by the EDC or if the
witness test is waived according to Article 2.1.1 of Appendix C.
Section 467.80 Disputes
a) A party shall attempt to resolve all disputes regarding interconnection in good
faith. A party shall provide prompt written notice of the existence of the dispute,
including sufficient detail to identify the scope of the dispute, to the other party in
order to attempt to resolve the dispute.
b) An informal meeting or conference call between the parties shall be held within
10 business days after receipt of the written notice. Persons with decision-making
authority from each party shall attend the meeting. In the event the dispute
involves technical issues, persons with sufficient technical expertise and
familiarity with the issue in dispute from each party shall also attend the informal
meeting. If parties agree, the meeting may be conducted by teleconference.
c) Subsequent to the informal meeting referred to in subsection (b), a party may seek
resolution of any disputes through the complaint or mediation procedures
available at the Consumer Services Division (CSD) of the Commission. Dispute
resolution at the Commission will be initially conducted in an informal,
expeditious manner to reach resolution with minimal costs and delay. If no
resolution is reached after informal discussions, either party may file a formal
complaint with the Commission.
d) Pursuit of dispute resolution shall not affect an interconnection applicant with
regard to consideration of an interconnection request or an interconnection
applicant's position in the EDC's interconnection queue.
Section 467.90 Records
a) An EDC shall maintain the following records for a minimum of three years:
1) The total number of and the nameplate capacity of the completed
interconnection requests received, approved and denied; and